The Project

Work packages & schedule

Five work packages, 24 months of implementation, 63 person-months of research.

Schedule

Implementation over 24 months

The schedule shows how the work packages overlap: the demand analysis (WP1) feeds the siting work (WP2), which in turn is embedded in the web application (WP3), while the research assessment (WP4) and the strategic plan (WP5) close the project.

Implementation schedule per work package (months 1–24)
WP \ Month123456789101112131415161718192021222324
WP1activeactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactive
WP2activeactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactive
WP3activeactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactive
WP4activeactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactive
WP5activeactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactiveactive
WP1WP2WP3WP4WP5
In detail

The five work packages

Months 1–12 12 person-months

The current state of demand for intermodal transport and of general freight traffic is recorded and analysed. Traffic flow is studied through an analysis of freight dynamics across the wider Thessaly region and along the main road and rail arteries passing through Larissa.

Available transport modes are examined, as well as the way the commercial port of Volos contributes to this freight traffic. In addition, the participation of the agri-food sector in the activities of the intermodal centre — and its influence on the centre's core functionalities — is estimated as accurately as possible.

Collection methodology

  • A series of targeted questionnaires to businesses, carriers and cooperative bodies.
  • Searches in public or semi-public data sources (associations, cooperatives, statistical services).
  • Re-use of deliverables from other research projects that produced comparable records.
  • On-site traffic observation over 12 months, so that seasonal variation (harvest period, tourist season) is captured.

Duration justification

12 person-months: extensive multi-source collection, 12-month monitoring of seasonal variation, processing with models and simulation tools, consultation with local stakeholders and preparation of detailed reports.

Resources

Distribution of person-months

Person-months per work package
WPTitleMonthsPerson-months
WP1Recording and analysis of intermodal transport demand, freight traffic flows and agri-food cargo1–1212
WP2Siting of the intermodal transhipment facility2–143
WP3Web application for traffic-load data management and siting optimisation models2–2427
WP4Dynamics and future prospects of an intermodal transport centre12–2413
WP5Development of a logistics strategic plan for the Region of Thessaly6–248
Total63