Work packages & schedule
Five work packages, 24 months of implementation, 63 person-months of research.
Implementation over 24 months
The schedule shows how the work packages overlap: the demand analysis (WP1) feeds the siting work (WP2), which in turn is embedded in the web application (WP3), while the research assessment (WP4) and the strategic plan (WP5) close the project.
| WP \ Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| WP1 | active | active | active | active | active | active | active | active | active | active | active | active | ||||||||||||
| WP2 | active | active | active | active | active | active | active | active | active | active | active | active | active | |||||||||||
| WP3 | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | |
| WP4 | active | active | active | active | active | active | active | active | active | active | active | active | active | |||||||||||
| WP5 | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active | active |
The five work packages
The current state of demand for intermodal transport and of general freight traffic is recorded and analysed. Traffic flow is studied through an analysis of freight dynamics across the wider Thessaly region and along the main road and rail arteries passing through Larissa.
Available transport modes are examined, as well as the way the commercial port of Volos contributes to this freight traffic. In addition, the participation of the agri-food sector in the activities of the intermodal centre — and its influence on the centre's core functionalities — is estimated as accurately as possible.
Collection methodology
- A series of targeted questionnaires to businesses, carriers and cooperative bodies.
- Searches in public or semi-public data sources (associations, cooperatives, statistical services).
- Re-use of deliverables from other research projects that produced comparable records.
- On-site traffic observation over 12 months, so that seasonal variation (harvest period, tourist season) is captured.
Duration justification
12 person-months: extensive multi-source collection, 12-month monitoring of seasonal variation, processing with models and simulation tools, consultation with local stakeholders and preparation of detailed reports.
Building on the results of WP1 — principally the freight analysis and the influence of the agri-food sector — the siting points for the intermodal transhipment facility are determined. These points are not selected empirically, but through mathematical optimisation models that evaluate parameters such as efficiency, cost, accessibility and demand coverage.
Once the models are built, an initial selection of candidate locations is made and evaluated against the optimisation results, with comparisons and, where needed, on-site assessments to confirm their viability and functionality.
Duration justification
3 person-months: study of WP1 results, construction and calibration of the optimisation models, evaluation of candidate locations and documentation of the methodology.
A web application is developed, offering functionality for (a) traffic-load data management, (b) geo-visualisation of siting data and (c) execution of the siting and traffic-analysis optimisation models. This phase produces essentially the entire software ecosystem used by the project.
Time breakdown per functionality
- Requirements analysis & functional design — 3–4 months
- Database & traffic-load data management — 4–5 months
- Geo-visualisation and spatial display — 3–4 months
- Integration of siting & traffic-analysis models — 4–5 months
- Quality assurance and testing (compatibility, performance, data security) — 4 months
- User training and documentation — 2–3 months
Duration justification
27 person-months: a complex application with many functionalities and demanding requirements for data management, analysis and geographic display.
Research assessment of areas related to the dynamics and future prospects of the centre:
- Management strategy and business plan (2–4 months) — mode of operation, services offered, expansion and adaptation plan, growth forecasts and the addition of new services.
- Economic viability (3–4 months) — performance, operating cost, profitability prospects and the diffusion of economic benefits across the Thessaly region.
- Legislation and regulatory framework (4–6 months) — transport, siting and environmental compliance law; safety requirements, permits and tax arrangements; procedures for compliance with national and European standards.
- Final report synthesis (1–2 months) — an implementation guide and presentation of results to stakeholders.
Duration justification
13 person-months: in-depth study, design and analysis across three core areas (management strategy, viability, regulatory framework) and synthesis of the final report.
A study for the development of a supply chain strategic plan for the Region of Thessaly, of which the intermodal freight centre forms one component. WP5 also organises the dissemination of the plan's conclusions.
- 3.5 months — Report on the participation of the intermodal centre as a key stakeholder of regional logistics within national logistics, its influence on Thessaly's commercial role, and support for agricultural production.
- 3 months — Report on increased connectivity, regional cohesion and the strengthening of the regional economy.
- 1.5 months — Design of the communication strategy and promotion of the centre's use through awareness actions.
Duration justification
8 person-months: design and description of the actions of the logistics development strategic plan for the Region of Thessaly.
Distribution of person-months
| WP | Title | Months | Person-months |
|---|---|---|---|
| WP1 | Recording and analysis of intermodal transport demand, freight traffic flows and agri-food cargo | 1–12 | 12 |
| WP2 | Siting of the intermodal transhipment facility | 2–14 | 3 |
| WP3 | Web application for traffic-load data management and siting optimisation models | 2–24 | 27 |
| WP4 | Dynamics and future prospects of an intermodal transport centre | 12–24 | 13 |
| WP5 | Development of a logistics strategic plan for the Region of Thessaly | 6–24 | 8 |
| Total | 63 | ||